1.
Activity Definition is
typically performed by which of the following:
a. Project Manager who created the WBS
b.
Project Team Members
responsible for the work package
c.
Project Officer
d.
Project Stakeholder
2.
Which of the following
is not an activity attribute:
a.
Person responsible for
the activity
b.
Location where to
perform the activity
c.
Time when to perform the
activity
d. Leads and Lags
3.
Which of the following
does NOT generate changes to the Project documents:
a. Define Activities
b.
Sequence Activities
c.
Estimate Activity
Resources
d.
Estimate Activity
Durations
4.
Which of the following
may generate a milestone list:
a.
Define Activities
b.
Sequence Activities
c.
Estimate Activity
Resources
d. Estimate Activity Durations
5.
In PDM, which of the
following relationships is rarely used:
a.
Finish-to-Start
b. Start-to-Finish
c.
Start-to-Start
d.
Finish-to-Finish
6.
A schedule activity may
begin 10 days before the predecessor activity finishes. This is an example of:
a. Finish-to-Start
b.
Start-to-Finish
c.
Start-to-Start
d.
Finish-to-Finish
7.
A schedule activity may
begin 10 days before the predecessor activity finishes. This is an example of:
a.
ADM
b. PDM
c.
A dependency with lag
d.
A dependency with lead
8.
The following BEST
describes a subnetwork:
a.
Precedence Diagramming
Method [PDM]
b. Arrow Diagramming Method [ADM]
c.
Fragment Network
d.
Activity-On-Node [AON]
9.
A Project Manager
in-charge of a Software Development projects is creating a project schedule
network diagram for the code development component of the project. This is an
example of:
a.
Precedence Diagramming
Method [PDM]
b.
Arrow Diagramming Method
[ADM]
c.
Fragment Network
d. Activity-On-Node [AON]
10.
What-if scenario
analysis is done as a part of which process:
a.
Sequence Activities
b.
Define Activities
c. Develop Schedule
d.
Control Schedule
11.
AON refers to:
a. Precedence Diagramming Method [PDM]
b.
Arrow Diagramming Method
[ADM]
c.
Fragment Network
d.
Mandatory Dependencies
12.
AOA refers to:
a.
Precedence Diagramming
Method [PDM]
b. Arrow Diagramming Method [ADM]
c.
Fragment Network
d.
Mandatory Dependencies
13.
Activity Resource Requirements
is an input to which of the following processes:
a.
Estimate
Activity Durations
b.
Control Schedule
c. Estimate Activity Resources
d.
Sequence Activities
14.
Dummy relationships or
dummy activities can be used in which of the following Activity Sequencing
techniques:
a.
Precedence Diagramming
Method [PDM]
b. Arrow Diagramming Method [ADM]
c.
Fragment Network
d.
Schedule Network
Templates
15.
Which of the following
is NOT an input to the Sequence Activities process:
a.
Project Scope Statement
b.
Activity Attributes
c.
Activity List
d. Change Requests
16.
Which of the following
is a technique for Sequence Activities:
a.
Precedence Diagramming
Method [PDM]
b.
Arrow Diagramming Method
[ADM]
c. Rolling Wave Planning
d.
Mandatory Dependencies
17.
Reserve Analysis is a
technique for:
a.
Define Schedule
b.
Sequence Activities
c.
Estimate Activity
Resources
d. Estimate Activity Durations
18.
Resource Leveling is a
technique for:
a. Develop Schedule
b.
Sequence Activities
c.
Estimate Activity
Resources
d.
Estimate Activity
Durations
19.
Following can be BEST
described as a kind of dependency that can create arbitrary float values and
limit scheduling options:
a.
Mandatory dependency
b. Discretionary dependency
c.
Start-to-Finish
dependency
d.
External dependency
20.
Critical path method is
used in which of the following processes:
a.
Sequence Activities
b.
Define Activities
c.
Develop Schedule
d. Estimate Activity Durations
21.
Parametric Estimating is
done as a part of which process:
a.
Sequence Activities
b.
Develop Schedule
c.
Estimate Activity
Resources
d. Estimate Activity Durations
22.
Identification of
Mandatory Dependencies is BEST done during which process:
a. Sequence Activities
b.
Develop Schedule
c.
Define Activities
d.
Estimate Activity
Duration
23.
Resource reallocation
from non-critical to critical activities is an example of which Project
Scheduling technique:
a.
Critical Path Method
b.
Schedule Compression
c.
What-if Analysis
d. Resource Leveling
24.
Knowledge of best
practices in a particular area is MOST likely to give rise to which of the
following dependencies:
a.
Finish-to-Start
dependency
b. Soft Logic
c.
Mandatory dependency
d.
External dependency
25.
A Project Manager is
preparing a Project Schedule network diagram. During the diagram development,
she removes a dependency between two tasks that was defined in an earlier
stage. After the network diagram is completed, she updates activity attributes
for the two tasks. This is an example of:
a.
Define Activities
b. Sequence Activities
c.
Develop Schedule
d.
Lack of change control
26.
Reserve Analysis
involves:
a.
Estimating by
multiplying the quantity of work by productivity rate
b.
Incorporating time
buffers into the activity duration estimates
c. Developing project schedule with contingency
reserves as a recognition of the schedule risk
d.
Adding resource reserves
to the activity resource estimates
27.
Which of the following
is not true for Resource Leveling:
a. Project schedule is build with resource buffers
to prevent schedule slippage
b.
Project’s Critical path
may be altered
c.
Resource based
scheduling method
d.
Reverse resource
allocation scheduling
Brown : Is what I selected
Green : Right answer
for the question that have only brown are correct
No comments:
Post a Comment